Status - Construction Project 3
TBD
Date last updated 11/21/2010
Footings and foundations Not started
Framing, sheathing, house wrap Not started
Shingling Not started
Windows and exterior doors Not started
Exterior cladding Not started
Porches, walks, driveway Not started
Rough electrical, plumbing, heating Not started
Insulation not started
Drywall Not started
Interior finish Not started
Kitchen cabinets and countertops Not started
Kitchen and bath Not started
Finish mechanical, electrical, plumbing Not started
Flooring Not started
Landscaping and cleanup Not started
Footings and foundations Not started
Framing, sheathing, house wrap Not started
Shingling Not started
Windows and exterior doors Not started
Exterior cladding Not started
Porches, walks, driveway Not started
Rough electrical, plumbing, heating Not started
Insulation not started
Drywall Not started
Interior finish Not started
Kitchen cabinets and countertops Not started
Kitchen and bath Not started
Finish mechanical, electrical, plumbing Not started
Flooring Not started
Landscaping and cleanup Not started
Report Made On
TBD